Projects Executed   

    TITAGARH GENERATING STATION [4 x 60 MW]

                                                              - commissioned in 1982-83

    SOUTHERN GENERATING STATION [2 x 67.5 MW]   

                                                          - commissioned in 1990-91

    BUDGE BUDGE GENERATING STATION [2 x 250 MW]

                                                    - commissioned in 1997-99               

    OPEN CAST COAL MINE at SARSHATALI [2.5 MTPA]  

                                                    - operated by ICML since 2002

Ongoing Projects

    1.250 MW Budge Budge Generating Station

                                                          [3rd unit extension.]

    2.40 MW Unit at Sarshatali Mine Head, Asansol

    3. Coal Washery Project at Sarshatali Mine Head

    Transmission System and Generation System

1.    132KV Kasba-East Cal ckt : September 2008

2.    EM S/S : December 2008

3.    132KV PRS- Kasba ckt : March 2009

4.    220KV BBGS-EM ckt : June 2009

5.    BBGS U3 : June 2009

6.    132KV TRS-Rishra ckt : March 2010

7.     Rishra S/S : March 2010

8.    220KV EM S/S-NCGS ckt : March 2012

9.    NCGS shutdown : March 2012

 

Forthcoming Projects

 A.2 x 300 MW Coal Fired Thermal Plant in  HALDIA

 B.2 x 500 MW Coal Fired Thermal Plant with Coal Mine in                                                                                     JHARKHAND

 C.2 x 500 MW Coal Fired Thermal Plant with Coal Mine in                                                                                          ORISSA

 D. 40 MW 2nd AFBC Unit at  SARSHATALI MINE HEAD